Progress of Projects
2025/2/28
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 64.67% | 64.47% |
2 | TIAA MRT Extension Line Project | 83.99% | 84.39% |
3 | Chiayi Urban District Elevated Railway Project | 49.30% | 49.31% |
4 | Tainan Urban District Railway Underground Project | 92.05% | 89.99% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 99.10% | 99.10% |
6 | TRA Pingzhen Temporary Station Project | 67.10% | 67.60% |
7 | Taoyuan Urban District Railway Underground Project | 42.33% | 32.42% |
8 | Hualien-Taitung Line Dual-Track Engineering Project | 41.20% | 29.51% |