 Project Management

Progress of Projects (May 2025)

Progress of Projects

2025/5/31

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 67.07% 65.81%
2 TIAA MRT Extension Line Project 84.73% 84.93%
3 Chiayi Urban District Elevated Railway Project 51.03% 51.05%
4 Tainan Urban District Railway Underground Project 74.24% 74.36%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.40% 99.40%
6 TRA Pingzhen Temporary Station Project 75.71% 76.88%
7 Taoyuan Urban District Railway Underground Project 43.54% 32.77%
8 Hualien-Taitung Line Dual-Track Engineering Project 48.34% 35.28%

 

Publisher:Railway Bureau, MOTC