Project Management

Progress of Projects (November 2024)

Progress of Projects

2024/11/30

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 63.21% 63.02%
2 TIAA MRT Extension Line Project 83.01% 83.40%
3 Chiayi Urban District Elevated Railway Project 47.52% 47.56%
4 Tainan Urban District Railway Underground Project 90.91% 88.73%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 98.80% 98.81%
6 TRA Fengming Temporary Station Project 100.00% 100.00%
7 TRA Pingzhen Temporary Station Project 59.58% 59.10%
8 Taoyuan Urban District Railway Underground Project 40.54% 32.12%
9 Hualien-Taitung Line Dual-Track Engineering Project 34.80% 25.10%