Project Management

Progress of Projects (November 2024)

Progress of Projects

2025/2/28

Item Project Scheduled Progress Actual Progress
1 the Additional TIAA MRT Airport Terminal 3 Station (A14) Project 64.67% 64.47%
2 TIAA MRT Extension Line Project 83.99% 84.39%
3 Chiayi Urban District Elevated Railway Project 49.30% 49.31%
4 Tainan Urban District Railway Underground Project 92.05% 89.99%
5 Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) 99.10% 99.10%
6 TRA Pingzhen Temporary Station Project 67.10% 67.60%
7 Taoyuan Urban District Railway Underground Project 42.33% 32.42%
8 Hualien-Taitung Line Dual-Track Engineering Project 41.20% 29.51%