Progress of Projects
2024/11/30
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 63.21% | 63.02% |
2 | TIAA MRT Extension Line Project | 83.01% | 83.40% |
3 | Chiayi Urban District Elevated Railway Project | 47.52% | 47.56% |
4 | Tainan Urban District Railway Underground Project | 90.91% | 88.73% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 98.80% | 98.81% |
6 | TRA Fengming Temporary Station Project | 100.00% | 100.00% |
7 | TRA Pingzhen Temporary Station Project | 59.58% | 59.10% |
8 | Taoyuan Urban District Railway Underground Project | 40.54% | 32.12% |
9 | Hualien-Taitung Line Dual-Track Engineering Project | 34.80% | 25.10% |