Progress of Projects
2025/5/31
Item | Project | Scheduled Progress | Actual Progress |
---|---|---|---|
1 | the Additional TIAA MRT Airport Terminal 3 Station (A14) Project | 67.07% | 65.81% |
2 | TIAA MRT Extension Line Project | 84.73% | 84.93% |
3 | Chiayi Urban District Elevated Railway Project | 51.03% | 51.05% |
4 | Tainan Urban District Railway Underground Project | 74.24% | 74.36% |
5 | Kaohsiung Urban Railway Underground Project (included Zuoying and Fengshan Project) | 99.40% | 99.40% |
6 | TRA Pingzhen Temporary Station Project | 75.71% | 76.88% |
7 | Taoyuan Urban District Railway Underground Project | 43.54% | 32.77% |
8 | Hualien-Taitung Line Dual-Track Engineering Project | 48.34% | 35.28% |